Evidence-Based Scheduling

Joel Spolsky’s article Evidence-Based Scheduling presents a method for generating reliable project timelines using historical data and probability distributions.

The Four Key Steps

  1. Break tasks into small units – Maximum 16-hour tasks force detailed thinking and prevent vague estimates like “implement Ajax photo editor”

  2. Track actual time spent – Developers log hours per task, creating a velocity history (estimate divided by actual time) that reveals individual estimating patterns

  3. Run Monte Carlo simulations – The system randomly samples from each developer’s historical velocities 100+ times to generate a probability curve showing likelihood of shipping on any given date

  4. Actively manage projects – Use distribution data to identify which developers need estimation help, whose workload should be reduced, and which features to cut

Key Insights

  • Interruptions and unpredictable work naturally get captured in velocity data
  • “A schedule is a box of wood blocks”—you can’t shrink tasks; you must either extend timelines or cut features
  • Only programmers doing the work should estimate it
  • Management-imposed tight schedules damage morale and productivity

My Takeaway

This approach transforms scheduling from wishful thinking into engineering. As a builder, I’ve found that honest schedules force better prioritization—often eliminating low-value features and improving the final product.